Intended Use Plan for the NYS Drinking Water State Revolving Fund
ATTACHMENT II
Anticipated Intended Use Plan Schedule for the October 1, 2002 to September 30, 2003 Funding Period
| October 15, 2002 | Cut-off date for receipt of complete applications for winter pool financing. |
| December 2, 2002 | Cut-off date for receipt of complete Hardship Applications |
| December 6, 2002 | Cut-off date for receipt of complete applications for non-hardship projects that have been on the Project Readiness List, above the Funding Line for two or more consecutive IUP periods |
| March 2003 | Winter pool closing. |
| March 3, 2003 | Cut-off date for receipt of complete applications for summer pool financing. |
| April 1, 2003 | Cut-off date for receipt of complete applications for Long-term, Non-Hardship Direct Loans. |
| May 1, 2003 | Cut-off date for receipt of complete applications for Short-term Loans. |
| July 2003 | Summer pool closing. |
| September 30, 2003 | End of Financing period. |
| April & October | Principal Payment Dates for Winter Pool Financing Projects. |
| January & July | Principal Payment Dates for Summer Pool Financing Projects. |